From Assemblymember Luz Rivas Desk – CalTrans Maintenance Update

#CalTrans Maintenance Update:

My office often gets calls about the status of the Interstate 210 Pavement Project. The project began in Summer 2020 and is expected to last through Winter 2023/2024. This project is a result of the $135.5 million project that will repave the roads from Wheatland Avenue to the I-5. These funds come directly from SB 1, the Road Repair and Accountability Act of 2017.
The I-210 Project will replace pavement on 52 lanes. On and off-ramps, connectors and adjacent shoulders will also be rehabilitated. Overhead sign structures, traffic loop detectors, center median barrier, and the guardrail system will be upgraded. The freeway lighting system and traffic signals at on and off-ramps will be improved. The project will also add stormwater treatment devices to eliminate trash from storm water drain systems.

All 55-hour weekend work has been completed. There are no roadwork plans scheduled. If there is, our office will notify the community via social media. Caltrans is on schedule to complete the major items of work by Summer 2023. To find out more details about this project, please visit: https://bit.ly/I-210freeway.

If you would like to get updates about the project via e-mail please contact my office at (818) 504-3911.